During a sprint review, what aspect of the completed work is commonly demonstrated?

Prepare for the Jira Software Essentials Associate Exam with interactive quizzes and detailed explanations. Master the topics and boost your confidence with our comprehensive study resources!

During a sprint review, the focus is primarily on demonstrating the work that has been completed in relation to the sprint goal. This event serves as an opportunity for the Scrum team to showcase the features or functionality that they have developed during the sprint. By highlighting how the completed work aligns with the sprint goal, the team can illustrate their progress and gather feedback from stakeholders.

Demonstrating completed work in context of the sprint goal emphasizes both the value delivered and the alignment with the overarching objectives set at the beginning of the sprint. Stakeholders can see firsthand how the outputs contribute to the project or product vision, facilitating spirited discussions on the next steps or adjustments needed for future sprints.

The other aspects mentioned, such as technical documentation, overall performance metrics, and financial implications, while they may have their places in a project, are not the central focus of a sprint review. The primary goal is to review and demonstrate what has been achieved, reinforcing a clear narrative about progress against the sprint goals.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy